Resolution 21-R-14: FDOT Utility Work Agreement for Capital Circle SW Widening Project
The Commission adopted a resolution authorizing a contract agreement with FDOT to relocate and construct water and sewer infrastructure for the Capital Circle Southwest Widening Project Segment 1. The total estimated cost is approximately $11.5 million for infrastructure work plus $1 million for FDOT project management, funded through Water Fund 466 and Sewer Fund 515.
How each commissioner voted
5 presentThe Motion
“Voted 5-0 to approve staff's recommendations presented in Item Nos. 9.01 - 9.03 on the Consent Agenda”
Adopted Resolution No. 21-R-14, authorizing the City Manager, or his designee, to execute a Utility Work of Highway Contract Agreement with Florida Department of Transportation (FDOT) for relocation and construction of water and sewer infrastructure to facilitate the construction of Segment 1 of the Capital Circle Southwest Widening Project.