New Senior Center Construction Manager at Risk Contract Award

Plain-language summary

The Commission unanimously approved the contractor ranking for the New Senior Center and authorized staff to negotiate a contract with the top-ranked firm, Culpepper / One Day Came, a joint venture. Commissioner Williams-Cox requested ongoing project updates. The contract was procured through RFT No. 120-20-RT.

✓ Reviewed by editor · Generated from source document, May 2026

How each commissioner voted

5 present

The Motion

As stated on the record

Voted 5-0 to approve the contractor ranking for the New Senior Center Construction Manager at Risk (CMAR) and to authorize staff to negotiate a contract with the top-ranked firm, Culpepper / One Day Came, a joint venture

Official agenda title

Approve contractor ranking for New Senior Center Construction Manager at Risk (CMAR) and authorize contract negotiation with top-ranked firm

📄BoardDocs · Jan 27, 2021 packet · page

Other Items from this Meeting

Full meeting record →
Item 10.01

Sidewalk Construction and Rehabilitation Services Contracts

Passed
Item 11.01

Citizen Police Review Board Appointments

Passed
Item 11.02

Affordable Housing Advisory Committee Appointments

Passed